New Baird School Updates
If you have questions or concerns regarding the new school, please fill out the District's community input form and someone will respond. Thanks.
Visit the Photo Gallery to view more pictures of the construction.
September 8, 2019 - Public Open House
August 19, 2019

June 28, 2019

April 30, 2019

December 21, 2018
.JPG)
November 14, 2018
Front of the new building

October 17, 2018
Front of the new building.

August 2, 2018
Gym walls are in place.

July 26, 2018

May 31, 2018
The groundbreaking celebration for the new Baird Elementary School was held on May 31, and construction has begun! View photos from the groundbreaking.
January 16, 2018
Bray Architects shared the preliminary exterior rendering for the new Baird Elementary School. Click on the pictures below to view a larger image of each rendering.

Preliminary exterior rendering

Preliminary exterior rendering

Preliminary courtyard rendering

Preliminary library rendering

Preliminary lunchroom rendering

Preliminary interior rendering
Bids issued: Thursday, February 20, 2018
Bids to be opened: Tuesday, March 20, 2018
Bid results and recommendations to the Board of Education at special Board meeting: April 2, 2018
Construction start (tentative): April 20, 2018
Construction complete (tentative): August 2, 2019
October 5, 2017
Bray Architects shared the conceptual plans for the new Baird Elementary School and asked for feedback until October 4,2017. Please click here to view a list of questions from community members, parents, and staff, and the answers provided by Bray Architects.
September 28, 2017
Video of the New Baird School Parent/Community Meeting Presentation
Please click the image below to view the new Baird school presentation. We apologize for the poor sound quality.

September 27, 2017
Bray Architects shared the conceptual plans for the new Baird Elementary School. Click on the links below to view a larger image of each plan.
Conceptual Floor Plan

Conceptual Site Plan

Upcoming Meetings for Input to New School Design
Parent/Community Meeting - Please join the Green Bay Area Public School District and Bray Architects on September 27, 2017 at 6 p.m. in the Baird School gym to review the conceptual designs for the new Baird Elementary School. This is your opportunity to provide feedback and ask questions.
Information will be available in the Baird office and on the District and Baird websites following the meeting. Parents and community members unable to attend the meeting may provide feedback on the preliminary designs until October 4, 2017 by filling out our community input form.
August 2017
The District is meeting with the City to discuss the site of the new school. The architects are currently in the preliminary design phase.
July 19, 2017
Bray Architects toured Baird teachers through three recent schools they designed in DeForest, Middleton and East Troy. The tours were important to provide staff input on different design elements and furniture.